ECHO SUMMIT SIDEHILL VIADUCT PROJECT

 
ECHO SUMMIT SIDEHILL VIADUCT Caltrans is conducting traffic safety roadwork to meet current safety standards. Over the lifetime of the bridge, natural wear-and-tear has occurred, necessitating standard repairs. These repairs will help ensure the safety of the bridge and help preserve this beautiful thoroughfare.

Announcements


HIGHWAY 50 CLOSURE AT ECHO SUMMIT POSTPONED

  • A full closure of U.S. Highway 50 over Echo Summit that was planned for mid-October is being postponed until next year.

  • The seven precast bridge girders needed for Echo Summit Sidehill Viaduct (bridge) Replacement Project will not be ready in time for an October closure. Instead, contractor Q&D Construction will winterize the job site and come back to finish the project next year.

  • This is a two-year project that the contractor was attempting to accelerate the work on. It is still on track to be finished on time next year.


CURRENT TRAFFIC CONTROLS

  • One-way traffic controls are in place weekdays 24/5, beginning Monday at 3 p.m. and ending at noon on Fridays weekly.

  • Expect up to 20-minute delays at Echo Summit Sidehill Viaduct (bridge).


Real-time Traffic Info


Project Timeline

Environmental Document Completed – December 2016
Right of Way Acquisition Completed – Spring 2018
Design Completed – Spring 2018
Advertise – Summer 2018
Begin Construction – Spring 2019
Expected Completion – December 2020